NA standing committee on Power Division apprised, DISCO not being privatized

Islamabad: (Web Desk) The National Assembly Standing Committee on Power Division was apprised that power distribution companies (DISCOs) were not being privatized. The committee, which met with Sardar Mehmood Khan Mazari in the chair, was further informed that recovery of those feeders having losses would be outsourced alone.

According to the Minister for Power Division Khurram Dastgir further told that it was imperative to eradicate power pilferage for reducing power tariffs. All big consumers would be switched on Advanced Metering Infrastructure (AMI) System by June, he added. He said around over 150,000 such consumers would be monitored live through the AMI System. Cheap electricity would be generated through solar energy while the quantity of electricity based on costly imported fuel would be minimized, he added.

As per details Khurram said “a point was being set up in Southern Punjab to control power breakdown as in the winter season, electricity was supplied from South to North. A cutout point would be set up to control county-wide power outages. National Transmission and Dispatch Company (NTDC) would set up cutouts for power blackouts. There were some feeders in the country where 98 per cent of people were not paying their bills.”

Furthermore he said “line losses could not be reduced without IT-based monitoring of the transmission system. He suggested in a camera meeting on power pilferage and electricity bills issues. The minister said that deferred bills of last year would be recovered from the consumers. Thar coal was being used in power generation and 1,980 MW of electricity was generated through local coal. The total power generation from local Thar coal would touch 2,640 MW in the coming summer season.”

Meanwhile briefing the NA Panel, the officials of NTDC said that line losses witnessed an upward trend during the last five years. The NTDC losses were technical and power theft was not included in it, they further said. The committee on a budgetary proposal for the next fiscal year 2023-24, the officials informed that the Power Ministry sought Rs.298 billion for 102 development projects under the annual public sector development program (PSDP).

Moreover out of the total 102 development projects, 81 were ongoing while 21 were new schemes, they said. They said out of the total allocation, Rs.122 billion was proposed under the local component and Rs.176 billion for the foreign component for the next fiscal year.

Comments are closed, but trackbacks and pingbacks are open.